Equipment
The world's first crane - to help build a national scenery large base
Seetao 2023-05-05 11:19
  • XCMG XCC2600 gallops the Gobi landform with powerful heavy-duty transition ability
  • XCMG XCC2600 has no faults in the construction process, high efficiency, and can complete the set goals in advance
Reading this article requires
7 Minute

Recently, one of the country's first batch of large-scale wind and solar base construction projects, Huadian North Xinjiang Urumqi 1 million kilowatts wind and rain base project, has been successfully connected to the grid.

The project is located in the Dabancheng wind area among the nine wind areas in Xinjiang. The 6.7MW wind turbine used is currently the largest single mountain wind power unit in my country. The hub height is 110 meters, which is equivalent to the height of a 40-story building. Two "world's first cranes" XCMG XCC2600 joined hands to help out, and began to participate in the project from the end of 2022, accelerating the project's grid-connected power generation.

XCMG XCC2600 is not timid when facing the wind turbine with the largest single-unit capacity of mountain wind power in my country. When the weather is good, it only takes 20 minutes to hoist the wind turbine in place, and the hoisting performance is strong. Not only that, in the case of carrying a total of 457 tons of main boom, super lift, outriggers, 40 tons of counterweight, etc., the chassis advantages are fully displayed, and it can ride the Gobi landscape with a powerful heavy-duty transition capability.

According to the situation at the construction site, XCMG XCC2600 can complete a 1-kilometer short-distance transfer between aircraft positions within 1 hour when facing muddy, ravines and other complex roads in the Gobi Desert of Xinjiang, which is convenient and fast.

With senior experience in the industry, Master Han, the operator of Wanxin Hoisting, is full of praise for XCMG XCC2600: "XCC2600 only needs two or three pallet trucks for short-distance transfer, and the efficiency of one is equal to three crawler cranes, which greatly reduces the operating costs. Cost. Moreover, the controllability is good, the ceiling fan is very stable, the micro-movement of the docking at a height of 100 meters is good, and the hoisting error of the rotary luffing is small, which is safer."

The excellent performance of "the world's first crane" also won the praise of the owner for Wanxin Hoisting. Manager Xue, the site manager of Wanxin Hoisting, said: "XCC2600 has no faults during the construction process, and the transfer efficiency is high. We have no rest during the Spring Festival. , accomplished the owner’s set goal ahead of schedule, and the owner rewarded us. I believe that we can develop better by cooperating with XCMG!”

It is understood that the project is expected to be fully completed and put into operation in 2023. After it is put into operation, more than 2.5 billion kwh of green electricity can be added every year, the annual saving of more than 830,000 tons of standard coal, and the reduction of carbon dioxide emissions by more than 2.1 million tons will effectively help energy consumption "double" The realization of the goal of "control" is of great significance to the construction of the core area of the Silk Road Economic Belt and the new energy large base market. Editor / Xie Li

Comment

Related articles

Equipment

73 mixing trucks from Sany brand successfully delivered to Southeast Asia

03-13

Equipment

The world's longest underwater high-speed railway tunnel shield machine offline

02-28

Equipment

Doosan Bobcat releases innovative hydrogen fuel cell forklifts

02-06

Equipment

Gold Core | Shantui DH24-G Working Condition Omnipotent King!

11-13

Equipment

Shantui SR36-G Roller's Strength Conquers Customers

10-31

Equipment

18 Taishan Pushing Electric Equipment Helps the Steel Industry

09-14

Collect
Comment
Share

Retrieve password

Get verification code
Sure